Submitted By:
Ryan Mulligan (ryantmulligan)
Category:
None
Percent Complete:
100%
Priority:
3
Start Date:
2006-07-23
End Date:
2006-07-30
Task Summary:
redirect_to
Original Comment:
A controller method that lets you run another command all the way through.
Assigned To
user_name
None
Dependent On Task
summary
Hours:
1
Status:
Open

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

No Comments Have Been Added

Task Change History

Field Old Value Date By
group_project_id2426 2006-08-02 23:17 ryantmulligan
dependent_on_id100 2006-08-02 23:17 ryantmulligan
percent_complete0 2006-07-29 17:04 ryantmulligan
end_date2006-07-30 2006-07-29 17:04 ryantmulligan
start_date2006-07-23 2006-07-29 17:04 ryantmulligan
dependent_on_id100 2006-07-29 17:04 ryantmulligan
summarycommand 2006-07-29 17:04 ryantmulligan
dependent_on_id100 2006-07-26 01:14 ryantmulligan
group_project_id2425 2006-07-26 01:14 ryantmulligan
dependent_on_id100 2006-07-26 01:13 ryantmulligan
end_date2006-07-29 2006-07-26 01:13 ryantmulligan
start_date2006-07-22 2006-07-26 01:13 ryantmulligan
status_id3 2006-07-26 01:13 ryantmulligan
status_id1 2006-07-26 01:12 ryantmulligan
dependent_on_id100 2006-07-26 01:12 ryantmulligan