Next Release: Browse Tasks | Gantt Chart | Reporting | Admin

Submitted By:
Michael Kelly (kellyclan)
Category:
Feature Request
Percent Complete:
100%
Priority:
3
Start Date:
2006-02-17
End Date:
2006-04-23
Task Summary:
Allow user to manually modify past activity times
Original Comment:
Currently, there is no way for the user to correct time spent on an activity if an activity was not closed at the proper time. For example, if the user goes to lunch and forgets to start the "lunch" activity, there is no way to correct this. It would be beneficial to provide the user with a view that allows them to manually modify time spent on past activities. This would build more flexibility into the application.
Assigned To
user_name
kellyclan
Dependent On Task
summary
Hours:
24
Status:
Closed

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

Followups

Comment Date By
This feature has been added and will be present in the next release. 2006-04-22 21:41 kellyclan

Task Change History

Field Old Value Date By
dependent_on_id100 2006-04-22 21:41 kellyclan
status_id1 2006-04-22 21:41 kellyclan
start_date2006-02-16 2006-04-22 21:41 kellyclan
end_date2006-04-23 2006-04-22 21:41 kellyclan
percent_complete0 2006-04-22 21:41 kellyclan
start_date2006-02-16 2006-04-22 21:41 kellyclan
end_date2006-04-23 2006-04-22 21:41 kellyclan
dependent_on_id100 2006-04-22 21:41 kellyclan