To Do: Browse Tasks | Gantt Chart | Reporting | Admin

Submitted By:
Doug Chasman (dchasman)
Category:
None
Percent Complete:
100%
Priority:
4
Start Date:
2006-01-31
End Date:
2006-02-07
Task Summary:
Multiple hetergeneous model support
Original Comment:
Allow for simultaneous connections to multiple/different adapters
Assigned To
user_name
dchasman
Dependent On Task
summary
Hours:
8
Status:
Closed

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

No Comments Have Been Added

Task Change History

Field Old Value Date By
status_id1 2006-02-02 21:49 dchasman
percent_complete20 2006-02-02 21:49 dchasman
start_date2006-01-30 2006-02-02 21:49 dchasman
end_date2006-02-06 2006-02-02 21:49 dchasman
dependent_on_id100 2006-02-02 21:49 dchasman