Pre-alpha release: Browse Tasks | Gantt Chart | Reporting | Admin

Submitted By:
Bert Meerman (bertm)
Category:
Documentation
Percent Complete:
100%
Priority:
3
Start Date:
2009-12-23
End Date:
2010-02-01
Task Summary:
Website - rationale explanation
Original Comment:
Explain on the website why the CBAC system is cool.
Assigned To
user_name
bertm
Dependent On Task
summary
Hours:
4
Status:
Deleted

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

No Comments Have Been Added

Task Change History

Field Old Value Date By
status_id2 2010-02-08 11:03 bertm
dependent_on_id100 2010-02-08 11:03 bertm
status_id1 2010-02-08 11:03 bertm
dependent_on_id100 2010-02-08 11:03 bertm
end_date2009-12-30 2010-02-08 11:03 bertm
dependent_on_id100 2010-02-08 11:03 bertm
percent_complete0 2010-02-08 11:03 bertm