Next Release: Browse Tasks | Gantt Chart | Reporting | Admin

Submitted By:
Norm Scherer (nsche)
Category:
code
Percent Complete:
100%
Priority:
3
Start Date:
2007-08-09
End Date:
2007-08-10
Task Summary:
Add print buttons where needed
Original Comment:
Add print button on most reports and also make checkin print out when completed.
Assigned To
user_name
nsche
Dependent On Task
summary
Hours:
10
Status:
Closed

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

No Comments Have Been Added

Task Change History

Field Old Value Date By
dependent_on_id100 2007-09-16 02:21 nsche
category_id100 2007-08-10 17:08 nsche
dependent_on_id100 2007-08-10 17:08 nsche
percent_complete0 2007-08-10 17:00 nsche
dependent_on_id100 2007-08-10 17:00 nsche
end_date2007-08-17 2007-08-10 16:59 nsche
start_date2007-08-10 2007-08-10 16:59 nsche
dependent_on_id100 2007-08-10 16:59 nsche
status_id1 2007-08-10 16:57 nsche
dependent_on_id100 2007-08-10 16:57 nsche