patir: Browse Tasks | Gantt Chart | Reporting | Admin

Submitted By:
Vassilis Rizopoulos (damphyr)
Category:
maintenance
Percent Complete:
100%
Priority:
5
Start Date:
2007-05-14
End Date:
2007-05-21
Task Summary:
move patir repository to Rubyforge
Original Comment:
Post a support request with the svn dump
Assigned To
user_name
damphyr
Dependent On Task
summary
Hours:
1
Status:
Closed

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

Followups

Comment Date By
Well, we didn't move the repository in the end. We just cehcked an export of the provate repo 2007-05-15 17:35 damphyr

Task Change History

Field Old Value Date By
dependent_on_id100 2007-05-15 17:35 damphyr
status_id1 2007-05-15 17:35 damphyr
percent_complete0 2007-05-15 17:35 damphyr
start_date2007-05-14 2007-05-15 17:35 damphyr
end_date2007-05-21 2007-05-15 17:35 damphyr
dependent_on_id100 2007-05-15 17:35 damphyr