Next Release: Browse Tasks | Gantt Chart | Reporting | Admin

Submitted By:
Gregor Schmidt (schmidt)
Category:
None
Percent Complete:
100%
Priority:
3
Start Date:
2007-05-09
End Date:
2007-05-09
Task Summary:
Complete Specs
Original Comment:
Convert all test to proper specs
Assigned To
user_name
schmidt
Dependent On Task
summary
Hours:
8
Status:
Closed

No Tasks are Dependent on This Task

No Related Tracker Items Have Been Added

Followups

Comment Date By
completed in r12 2007-05-09 14:29 schmidt

Task Change History

Field Old Value Date By
dependent_on_id100 2007-05-10 11:23 schmidt
start_date2007-05-09 2007-05-09 14:31 schmidt
end_date2007-05-16 2007-05-09 14:31 schmidt
dependent_on_id100 2007-05-09 14:31 schmidt
status_id1 2007-05-09 14:29 schmidt
dependent_on_id100 2007-05-09 14:29 schmidt
percent_complete0 2007-05-09 14:29 schmidt
start_date2007-05-09 2007-05-09 14:29 schmidt